Telecomunications worksheet
  Electrical Outside Plant / Fiber Contractor Communications Contractor Boise State
  Install conduit(s) in Telecom Floor (4inch collar above floor grade)   x    
  Install Telecomunications Building Ground (bond to building structure, install offset face plate / per specifications) x      
  Test Telecomunications Building Ground (TBC) according to specifications x      
  Forwared TBC test results to Boise State x      
  Install horizontal tray and steel 4" inch pipe through firewalls x      
  Bond horizontal steel (tray and pipe)  to floor TBC x      
  Install racks and rack management in Telecoms     x  
  Bond racks in Telecoms to TBC     x  
  Connect conduit from Entrance Facility (EF) room to outside conduit system   x    
  Install interduct in conduit from EF to designated Hub Facility (HF) (fill any conduit used with interduct)    x    
  Install fiber and copper (per specifications) from EF to HF   x    
  Install Lightning Protectors on copper at both  EF to HF     x  
  Terminate copper on patch pannel (per specification) at both  EF and HF     x  
  Terminate and install connectors on all fiber at both  EF and HF (all single mode fiber will be fusion spliced at connections)  Install all fiber into fiber trays (per specifications)   x    
  Label all copper and fiber ends (per specifications)   x x  
  Test copper and fiber per specifications between  EF and HF   x x  
  Forward copper and fiber tests results to Boise State   x x  
  Install vertical copper and fiber between Telecos, terminate ends, install in patch panels or fiber trays (per specifications)   x x  
  Test vertical copper and fiber between Telecos   x x  
  Install horizontal copper, terminate ends in patch pannels (per specifications)     x  
  Test horizontal copper      x  
  Forward horizontal copper test results to Boise State     x  
  Verify electrical outlets in Telecoms are functional x      
  Change construction lock on Telecom doors to Boise State key       x
  Note:  at this point temporary analog lines or data connects may be requested (2 weeks notice)        
  Label all copper and fiber ends in Telecoms (per specifications)     x  
  Request phone line for elevators     x  
  Install phone line for elevators       x
  Request phone line for alarm panel     x  
  Instlal phone line for alarm panel       x
  Request data line for alarm panel, smart building controller, etc     x  
  Install data line for alarm panel, smart building controller, etc       x